Casa Circo pool houseDone
Circo House · Albufeira · 6 October 2025 → 24 April 2026
Budget €0
Spent so far €0
Left in budget €0
Invoiced in 2026 €0
Progress vs spending
100%done
Monthly cost · 2026€33,825.00 Jan–Oct
January€10,049.01
JanFebMarAprMayJunJulAugSepOct
Milestones
- Survey6 Oct 2025
- Design8 Nov 2025
- Licences11 Dec 2025
- Structure13 Jan 2026
- Services16 Feb 2026
- Finishes21 Mar 2026
- Handover24 Apr 2026
Invoices · 2026Everything is paid
| Invoice | Stage | Status | |||
|---|---|---|---|---|---|
| FT 2026/128 | Stage 1 | 23 Jan 2026 | Paid | €6,645.32 | |
| FT 2026/129 | Stage 2 | 28 Feb 2026 | Paid | €4,430.22 | |
| FT 2026/130 | Stage 3 | 5 Apr 2026 | Paid | €5,537.77 | |
| Total invoiced | €16,613.31 |
Crew on this job
- TTiago
- AAna